Hello,
I have several tasks where they are dependant on each other. The start date
for each task (not including the first one) starts on the same day the
previous tasks ends. I want to automatically make sure each new task starts
the following day teh previous tasks ends. I tried everything from changing
task types (ie: fixed Duration, Fixed work), taking out resources that have 0
hrs. Nothing seems to work. Does anyone know what is going on??
Task name - Work - Actual Work - Duration - Start - Finish
Review of Beta Release 0 hrs 0 hrs 2 days Tue 5/3/05 Wed 5/4/05
Beta Changes (CRW) 74 hrs 0 hrs 8 days Wed 5/4/05 Tue 5/17/05
Beta QAP Verification (IRW) 12 hrs 0 hrs 1 day Tue 5/17/05 Wed 5/18/05
Package / Deploy / Release Notes 10 hrs 0 hrs 2 days Wed 5/18/05 Fri 5/20/05
Any advice would be helpful!!
I have several tasks where they are dependant on each other. The start date
for each task (not including the first one) starts on the same day the
previous tasks ends. I want to automatically make sure each new task starts
the following day teh previous tasks ends. I tried everything from changing
task types (ie: fixed Duration, Fixed work), taking out resources that have 0
hrs. Nothing seems to work. Does anyone know what is going on??
Task name - Work - Actual Work - Duration - Start - Finish
Review of Beta Release 0 hrs 0 hrs 2 days Tue 5/3/05 Wed 5/4/05
Beta Changes (CRW) 74 hrs 0 hrs 8 days Wed 5/4/05 Tue 5/17/05
Beta QAP Verification (IRW) 12 hrs 0 hrs 1 day Tue 5/17/05 Wed 5/18/05
Package / Deploy / Release Notes 10 hrs 0 hrs 2 days Wed 5/18/05 Fri 5/20/05
Any advice would be helpful!!