S
sanju
I am not able to see hyperlinks for predecessors in the Task drivers
pan that belong to a sub project in MS project 2007. Is there any way
to make this work?
Also I am not able to see the ghost tasks in master file even if I
turn on show external predecessor/successor options in tools ->
options-> view
I do have links from master to child and child to master and still the
ghost links don't display. I was thinking if I could display these
then may be clicking the ghost link would open the child project and
select the driving predecessor and I could use task drivers in that
file to proceed further.
pan that belong to a sub project in MS project 2007. Is there any way
to make this work?
Also I am not able to see the ghost tasks in master file even if I
turn on show external predecessor/successor options in tools ->
options-> view
I do have links from master to child and child to master and still the
ghost links don't display. I was thinking if I could display these
then may be clicking the ghost link would open the child project and
select the driving predecessor and I could use task drivers in that
file to proceed further.