60% means 60% of the time .... every day. This is not the same as 3 days per
week.
Fred: 4 days x 8 hours/day x 100% = 32 hours work (8 hr/day)
Barny: 4 days x 8 hours/day x 60% = 19.2 hours work (4.8 hr/day)
If Barny can only work 3 days/week, MS Project has no way to know which
three days are available and which 2 days are off. You will need to create a
unique calendar for Barny showing his availability. You can do that by
double clicking on Barny in the Resource Sheet and customizing his work
calendar.
I think what you want is:
Fred: as before 32 hours full time
Barny: 32 hours (4 days x 8 hours)
Try changing Barny's availabilty to 60% units on the resource sheet. If I
enter the work as these value Project calculates the duration as Gerard
indicates. So you first need to decide how much work is involved. Is it a 4
day task with 1.6 heads or a 64 hour task with 1.6 heads of availability on
any given day?
To answer your other question, the units for entering data can be changed
fromTools/Options then pull the Scheduling Tab. Keep in mind, this only
changes the display and the entry method, not the calculations. Project
actually does everything in minutes.
--
If this post was helpful, please consider rating it.
Jim
Check out my new blog for more information:
http://www.msprojectblog.com