Task duration "auto-stretch"

  • Thread starter Luis Felipe S. Monteiro
  • Start date
L

Luis Felipe S. Monteiro

Hello All,

I want to create a task named "Project monitor and control" that occurs
as long as the project. But this task should be automatically adjusted
when the project duration increase ou decrease.

Is it possible? What link type should I use?

Thanks,

Luis Felipe S. Monteiro
 
L

Luis Felipe S. Monteiro

Yes! That´s it!

Thanks for the instructions. They worked perffectly!

Best regards,

Luis Felipe
 