C
ccannon
Hi,
Is there a way to automatically set the start and finish dates of a
task based on the start and end dates of other tasks?
For example, I'm budgeting for a project that includes a Project
Manager assigned to oversee the execution of a given set of tasks. I
estimate the Project Manager will spend 10% of his time managing it.
The first task starts on day 1 followed by a number of other tasks, the
last one ending on day 15. Is there a way to have the Project Manager's
-management task- automatically span the 15 days, with just 10% of his
time allocated during that period?
I'm hoping for an automatic duration solution so I can adjust the
durations of the other tasks and have the Project Managers task update
automatically.
Thanks for your help.
-C
Is there a way to automatically set the start and finish dates of a
task based on the start and end dates of other tasks?
For example, I'm budgeting for a project that includes a Project
Manager assigned to oversee the execution of a given set of tasks. I
estimate the Project Manager will spend 10% of his time managing it.
The first task starts on day 1 followed by a number of other tasks, the
last one ending on day 15. Is there a way to have the Project Manager's
-management task- automatically span the 15 days, with just 10% of his
time allocated during that period?
I'm hoping for an automatic duration solution so I can adjust the
durations of the other tasks and have the Project Managers task update
automatically.
Thanks for your help.
-C