M
Mahesh Narkar
Hi,
I am using MSP 2K3 SP2.
I have a problem in one of my schedules (say "Today") where a task duration
increases. There is an error observed prior to this increase, when modifying
another task - likely not linked to the task where the duration increases.
The error reads - "The resource is assigned outside the original dates for
task 1234 Task Description in project "Combined". The duration of this fixed
duration task will change to accomodate the resource assignment"
Note I had used "Combined" to populate the resource pool in the current
schedule, however, all links have been broken and "Today" uses "Own
resources".
Task Type is Fixed Duration with the Effort Driven Checkbox ON
I have a hard time keeping the updates lined up to the targets set and would
appreciate any pointers on how to resolve this.
Thanks in advance,
Cheers
Mahesh
I am using MSP 2K3 SP2.
I have a problem in one of my schedules (say "Today") where a task duration
increases. There is an error observed prior to this increase, when modifying
another task - likely not linked to the task where the duration increases.
The error reads - "The resource is assigned outside the original dates for
task 1234 Task Description in project "Combined". The duration of this fixed
duration task will change to accomodate the resource assignment"
Note I had used "Combined" to populate the resource pool in the current
schedule, however, all links have been broken and "Today" uses "Own
resources".
Task Type is Fixed Duration with the Effort Driven Checkbox ON
I have a hard time keeping the updates lined up to the targets set and would
appreciate any pointers on how to resolve this.
Thanks in advance,
Cheers
Mahesh