It is usually easier to diagnose what's actually happening if you go to the
Tools Options menu, the View tab, and choose to display dates in a format
that also includes the time.
As John pointed out, durations are ALWAYS stored and calculated internally
in minutes to the nearest 10th, regardless of the units you enter or display
duration in. It is impossible to force Project to use any other base units
such as whole days or calendar weeks or months - when you see "1 d"
displayed, it is only an approximation for convenience sake and the real
duration value is 480.0 (when using the default calendars and settings).
The status of the "estimated" flag has no impact on duration calculations -
it's merely to serve as a reminder to the PM to revisit the projected task
duration before locking down the plan.
The answer to your puzzle lies somewhere in the details links and the
calendars you've assigned to the various tasks but without seeing the actual
plan it's impossible to say where. But the occurance of fractional days in
the summaries is not at all unusual and if you display the times you'll see
that a summary task starting, say, next Monday that has a displayed duration
of 2.75 days will have it's earliest starting subtask beginning Mon at 8am
and its latest finishing subtask ending Wed at 3pm (assuming the default
calendars).
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
katalinc said:
Yes, I am talking about the project summary task. But what is
interesting is that some sub tasks were doing the same thing when I
checked the "estimated" box next to duration on a sub-sub-task. As soon
as I unchecked those boxes the sub-tasks became round numbers but the
summary task is still not a round number.
The problem is, that I have no resources assigned to anything. I am
using project to create an architectural schedule. This is all meetings
and tasks that have a set time duration (in days).
Is there a way I could tell all tasks to start at the same time? I am
really a very basic user and I am not even sure where I could check if
the start times are consistent. I have been using whatever was default
and have not changed it - intentionally. As far as the task information
dialog box goes every task is a full day or multiples of full days...
One more thing that may be contributing to this - and tell me if this
is a possible issue- I have a section of the project where we have to
count calendar days. The other parts of the project are set to count
working days. But they are still full days so I am not sure if this is
what would cause the total count to not be a full day amount. Both of
the calendar settings count a full day from 8-5.
Thank you for your help.
--
katalinc
------------------------------------------------------------------------
katalinc's Profile:
http://forums.techarena.in/members/katalinc.htm
View this thread:
http://forums.techarena.in/microsoft-project/1125256.htm
http://forums.techarena.in