CookieBurkhalter
I have a task that took two people 8 hours each consecutively. They worked
this actual time over 5 physical work days. When I entered the task into
Project 2007, I entered the task as Fixed Duration and I entered the two
resources with units set to 8h each, rather than a percentage. When tracking
the task, in Actual Start date I entered Monday and in Actual Finish date, I
entered that Friday. Project changed the units to 100% for each resource and
changed the actual end date to Tuesday.
How do I show that although the task was 8 hours for each person, they took
a week to finish it (because they are working on other things)?
Thanks in advance.
this actual time over 5 physical work days. When I entered the task into
Project 2007, I entered the task as Fixed Duration and I entered the two
resources with units set to 8h each, rather than a percentage. When tracking
the task, in Actual Start date I entered Monday and in Actual Finish date, I
entered that Friday. Project changed the units to 100% for each resource and
changed the actual end date to Tuesday.
How do I show that although the task was 8 hours for each person, they took
a week to finish it (because they are working on other things)?
Thanks in advance.