B
Bill Reicheld
How can you enter a task duration that is longer than the
resource time allocated? For example, if I enter a task
of "Advertising Budget"; working on the budget may start
on Oct. 1 and end Oct. 30, but the actual billing time
may only be 40 hours over the 30 days. So I want my cost
of this task to be "40 hours x $RATE" not "30 days x
$RATE". At the same time I want to show the task
duration over 30 days. I'm using Project 2000 in case
that makes any difference.
resource time allocated? For example, if I enter a task
of "Advertising Budget"; working on the budget may start
on Oct. 1 and end Oct. 30, but the actual billing time
may only be 40 hours over the 30 days. So I want my cost
of this task to be "40 hours x $RATE" not "30 days x
$RATE". At the same time I want to show the task
duration over 30 days. I'm using Project 2000 in case
that makes any difference.