Task duration

S

saws

Hi,

I have an activity1 spanning 8.2 days, activity 2 spanning 3.8 days. Both
run in parallel- they have the same predecessors and successors. There are no
other activities for the given task. So logically the task level duration
should be the longer of the two, that is 8.2 days. But MSP shows the task
duration as 6.9 days. Can anybody please explain this?

Thanks,
Saws
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top