Hello,
i am running MS Project 2007 and i want to add a task with a duration of
4hrs, however i don’t mind what date the task is completed on; just that it
be completed by a certain set date.
How can i set this up? Please help.
So basically i want to have a sort of "floating" task which needs to be
completed by a set date but not necessary straight away.
Thank You
Yoni - You have the *duration* has 4 hours and want the task finish
not later a certain date. Since, you have not indicated whether you
have multiple or single resource assignment to this task, I assume you
have multiple resources assigned.
I provide two solutions - (1) Using Constraints + Task Type (2) Using
Deadlines + Task Type
First the (1) Using Constraints + Task Type solution.
Before, I go to the steps, add "Work" field as column to your Gantt
chart. So, now the steps
a. Double click the task to get the Task Information dialog
b. Select "Advanced" tab
c. Choose the constraint type as "Finish No Later Than" (that is
latest date by which the task can finish) and provide your "fixed"
date as constraint date
d. Set the "Type" as "Fixed duration"
e. [Optional - Only for multiple resources] Set the "Effort-driven" to
"Yes", if want the task "Work" to be constant and close the dialog
box.
f. In Gantt Chart view, set the "Duration" to 4 hours; you will
observe the "Work" and "Resource" assignment units will change
appropriately.
Effectively, the above steps indicate that the task duration is fixed
and constraint is placed.
Warning! If the predecessor of the task that has "Finish No Later
Than" constriant is delayed beyond its slack time, it will create a
scheduling conflict.
Now, the second solution (2) Using Deadlines + Task Type. Follow the
same set of steps, except in the "Advanced" tab, set the "constraint"
type as "as soon as possible" and set your "fixed date" in the
"Deadline" field.
If this answers your question, please consider rating it
- Sai, PMP, PMI-SP, MCT, MCTS
http://saipower.wordpress.com