E
easyrider
I noticed a difference between the task duration and the task start and
finish dates and I am not sure that I understand why the difference. For
example if I start a task on April 21, 2006 (Friday) and set the weekend to
be normal working hours, and set the finish date to be Monday April 24, 2006,
why doe usoft project 2003 only show 3 days for duration?
finish dates and I am not sure that I understand why the difference. For
example if I start a task on April 21, 2006 (Friday) and set the weekend to
be normal working hours, and set the finish date to be Monday April 24, 2006,
why doe usoft project 2003 only show 3 days for duration?