Task duration

T

Tarmo

Hi

How can I view (if duration is entered in days) task/project duration in
edays?

Br,
Tarmo
 
G

Gérard Ducouret

Hello Tarmo,
Insert a custom field (Number1 may be) besides the Duration field for
example.
Right Click the caption / Customize / Formula :
DateDiff("d";[Start];[Finish])
For Summaries, Click the Use a Formula option.

Hope this helps,

Gérard Ducouret
 