Task duration

N

neostar77

I have a 3-day task for one resource.

However, if I add another resource, I want Project to automatically trim
down the duration to 1.5 days.

How should I go about doing that?
 
J

Jim Aksel

Makethe task Fixed Units, Effort Driven. (Window/Split...) it is the bottom
window. Check the effort driven box. Now, adding resources divides the
**remaining work ** among all resources present in accordance with their
assigned percentages. Task duration decreases.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
D

Dave

neostar77 said:
I have a 3-day task for one resource.

However, if I add another resource, I want Project to automatically trim
down the duration to 1.5 days.

How should I go about doing that?

Ensure that the task type is fixed work and it should occur automatically.
 
S

Steve House [MVP]

If you are adding another resource name to the task - ie, Joe is assigned
and you're adding Bill - marking it "effort driven" before adding the
resource will do it. If you're changing the assignment percentage - you
have "Carpenters, 100%" assigned and you're making it "Carpenters, 200%" -
mark the task "fixed work" before doing the edit.
 