K
Kurt
I've searched the discussion group and have not found anyone with exactly
this same issue.
If I create an new task and assign a duration of 1 mon, Project calculates a
duration in excess of that (e.g. Start = 8/1 Calculated Finish = 9/12). The
same is true for any number of months (e.g. 2 month duration, start = 8/1,
calculated finish = 10/27). I have no resources are assigned, no
contigencies, and I have checked the calendar and work time, and nothing
seems incorrect. Also, the calcuated durations for days and weeks appear to
be correct (hence, I've been using those instead of months). I have a work
around but my inability to solve this issue is driving me nuts. Any
assistance it greatly appreciated.
this same issue.
If I create an new task and assign a duration of 1 mon, Project calculates a
duration in excess of that (e.g. Start = 8/1 Calculated Finish = 9/12). The
same is true for any number of months (e.g. 2 month duration, start = 8/1,
calculated finish = 10/27). I have no resources are assigned, no
contigencies, and I have checked the calendar and work time, and nothing
seems incorrect. Also, the calcuated durations for days and weeks appear to
be correct (hence, I've been using those instead of months). I have a work
around but my inability to solve this issue is driving me nuts. Any
assistance it greatly appreciated.