Can anyone tell me why Project 98 will display a duration
for a summary task that is something like 4.67 days when
the four subtasks are each one day in duration and
sequential?
Thanks!
for a summary task that is something like 4.67 days when
the four subtasks are each one day in duration and
sequential?