Task durations to 2 decimals

E

Emma

Hi

I have a problem in msp2000 that is making me lose it!
I have a standard company calender, and a 7.00 standard hour day. As soon as I change a subtask from 'As Soon As Possible' (project start date) to 'Must Start On' (any date following the project start date) the task header shows the total duration as decimals - ie 7.86days. This happens even when all tasks in the group are duration 0d.

Any ideas?
 
M

Mike Glen

Hi Emma,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP

Hi

I have a problem in msp2000 that is making me lose it!
I have a standard company calender, and a 7.00 standard hour day. As soon
as I change a subtask from 'As Soon As Possible' (project start date) to
'Must Start On' (any date following the project start date) the task header
shows the total duration as decimals - ie 7.86days. This happens even when
all tasks in the group are duration 0d.
 