Hi
I have a problem in msp2000 that is making me lose it!
I have a standard company calender, and a 7.00 standard hour day. As soon as I change a subtask from 'As Soon As Possible' (project start date) to 'Must Start On' (any date following the project start date) the task header shows the total duration as decimals - ie 7.86days. This happens even when all tasks in the group are duration 0d.
Any ideas?
I have a problem in msp2000 that is making me lose it!
I have a standard company calender, and a 7.00 standard hour day. As soon as I change a subtask from 'As Soon As Possible' (project start date) to 'Must Start On' (any date following the project start date) the task header shows the total duration as decimals - ie 7.86days. This happens even when all tasks in the group are duration 0d.