P
Pam S.
Greetings,
I am having a problem converting task durations to calendar durations in MS Project Standard 2003.
The project calendar is set for a 5-day work week.
Hours per day: 8.00
Hours per week: 40.00
Days per month: 20
Task durations are entered in days in the "Duration" field.
I need to show actual calendar days, so I customized "Duration1" with the following formula: CDate([Finish]-[Start])
The calendar durations end up with a .38 afterwards, i.e., 24.38, 25.38, 18.38, 4.38.
Is there a quick fix to get the calendar durations to display as whole days? I tried the "Rnd(number)" formula but that didn't work.
Many Thanks!
Pam S.
I am having a problem converting task durations to calendar durations in MS Project Standard 2003.
The project calendar is set for a 5-day work week.
Hours per day: 8.00
Hours per week: 40.00
Days per month: 20
Task durations are entered in days in the "Duration" field.
I need to show actual calendar days, so I customized "Duration1" with the following formula: CDate([Finish]-[Start])
The calendar durations end up with a .38 afterwards, i.e., 24.38, 25.38, 18.38, 4.38.
Is there a quick fix to get the calendar durations to display as whole days? I tried the "Rnd(number)" formula but that didn't work.
Many Thanks!
Pam S.