A
abhi
Hi,
When I accepted updates for some tasks, it saved actuals in Project but
its end date is shifted to 12/31/2049. Work, Actual Work, Remaining
Work fields are showing correct values only the end date is shifted.
Can anyone help me understand what may have gone wrong?
Thanks.
When I accepted updates for some tasks, it saved actuals in Project but
its end date is shifted to 12/31/2049. Work, Actual Work, Remaining
Work fields are showing correct values only the end date is shifted.
Can anyone help me understand what may have gone wrong?
Thanks.