N
Nate Birkholz
When I create a task in Project, assign it a work value, and confirm the
duration, it has the task end at the same time as the next task starts. For
example, from my latest schedule:
Task Name Work Duration Start End
Task 1 16 hrs 2 days Wed 1/9/08 Fri 1/11/08
Task 2 8 hrs 1 day Fri 1/11/08 Mon 1/14/08
The tasks definitely start first thing in the morning. Is it possible to
have the tasks end on the day they really end?
The reason I ask is because it is a lot of extra work when I copy the
columns out of Project and paste them into Excel to give them to the team. I
have to go through and remove one workday from the Finish column.
duration, it has the task end at the same time as the next task starts. For
example, from my latest schedule:
Task Name Work Duration Start End
Task 1 16 hrs 2 days Wed 1/9/08 Fri 1/11/08
Task 2 8 hrs 1 day Fri 1/11/08 Mon 1/14/08
The tasks definitely start first thing in the morning. Is it possible to
have the tasks end on the day they really end?
The reason I ask is because it is a lot of extra work when I copy the
columns out of Project and paste them into Excel to give them to the team. I
have to go through and remove one workday from the Finish column.