Hi

I am facing a problem here. I am working to Extend OLAP cube for task
fields. I followed and OLAP Extension guidelinee (Sol. Starter for
Project server 2003) and code and extend the cube. Every thing is fine
but i can not see any data inside the cube. I have checked the cube in
Analysis manager and checked the data inside the referenced tables.
the tables has task data like task id, project id but the task fields
like task work, task cost, etc.. are 0 or blank. I also noticed that
the black rows are the projects where project cost data is available.
I will be thankful if some could help me in this regard,

Regards

Jerry
 
G

Guest

Hi Jerry,

There are a lot of details in this process that are easy to overlook. I wrote
a white paper to supplement the Microsoft earned value example and it
might help you get started. You can download the paper and example code
from:

http://bsege.com/white_papers.htm

Bob Segrest, PMP
Microsoft Project Blackbelt
 
J

Jerry

Hi Bob

fortunately i read your annoucement here in the forum about the white
paper and downloaded that. I just gave it a quick try by following the
same old data but still no result. But sure going to follow your
guide. and by the way you did a great job man. I also tried to write
some simple stuff on that but got stuck at last step. I also blog
about your white paper and refered to many people who are working on
it. my blog address is http://www.jerryyasir.blogspot.com

Regards

Jerry
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top