A
Adam Goodman
I have multiple projects and have published them in PS using a global
resource pool.
The subprojects in each project are basically a Part going through tasks
which has a resource assigned to it.
I would like to put that Part number in a field to report on later. The
report would break down by grouping Resource then having the name of the task
and the Part number plus start and end.
I have tried populating Text1 in the Gantt chart view but these do not show
up in Resource Usage view. They are 2 different Text1 fields.
Is there way to do this? I am trying to use PWA and no view will help me. I
have also tried just with Project. It also looks like the Analyzer won't help
either but my eyes are becoming crossed.
Help would be greatly appreciated!
ADam
resource pool.
The subprojects in each project are basically a Part going through tasks
which has a resource assigned to it.
I would like to put that Part number in a field to report on later. The
report would break down by grouping Resource then having the name of the task
and the Part number plus start and end.
I have tried populating Text1 in the Gantt chart view but these do not show
up in Resource Usage view. They are 2 different Text1 fields.
Is there way to do this? I am trying to use PWA and no view will help me. I
have also tried just with Project. It also looks like the Analyzer won't help
either but my eyes are becoming crossed.
Help would be greatly appreciated!
ADam