S
Stacey S.
We utilize project and Project Server 2007.
Using the Gantt Chart view, the finish date for Task A (duration based) is
1/10/10. If I double click on the task in either the Task Usage or Resource
Usage views, the end date is early December. This (I think) is causing the
resource hours to be "front-loaded" i.e. no planned work is present for
December or early January.
I've double checked for constraints.
Additional Information: The time planned for Sept-Nov was higher than the
actual hours used. What is the best way to change this so the plan reflects
reality?
Thanks!
Using the Gantt Chart view, the finish date for Task A (duration based) is
1/10/10. If I double click on the task in either the Task Usage or Resource
Usage views, the end date is early December. This (I think) is causing the
resource hours to be "front-loaded" i.e. no planned work is present for
December or early January.
I've double checked for constraints.
Additional Information: The time planned for Sept-Nov was higher than the
actual hours used. What is the best way to change this so the plan reflects
reality?
Thanks!