task fixed cost in time phased data

S

szabti

Hi, all,

I have a Project Server 2003 based project with hundred of tasks. I test
fixed cost behavior, and noticed the next:

I put 1 million (it is stored in project server as 100 000 000) on heading
started 16 Sept 2006, finish at 8 May 2009, extract TP data while saving
project, publish it to the server. Then I check it in my excel pivot table,
based on stored procedure ( using table MSP_VIEW_PROJ_TASK_TP_BY_DAY and
others), and I get back 100 000 320.

What is this difference 320? How can I avoid it?

thanks,


szabti
 