Task for Project Management

T

The Project Master

I would like to create an overall project summary task called "Project
Management" that begins on the start date of the first detail task & ends on
the finish date as the last detail task. As each of the tasks of the project
are changed (e.g., duration, start & end dates), I would like this summary
task to also adjust as the # of the hours on
the project changes. I would then like to assign a project manager to the
"Project
Management" task at a specific hourly rate and then have that task included
in the project reports with its associated cost.

Can anyone assist me?

Thanks for your assistance.
 
M

Mike Glen

Hi ,

Welcome to this Microsoft Project newsgroup :)

Please see FAQ Item: 19. Hammock Tasks.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 