tom wilson
I am new to MSP 2003 Standard
Can someone explain how I do the following:-
I have a task that runs over an elapsed time of 6 weeks but the actual work
lasts for
8 non contiguous days.
Its like scheduling a fortnightly meeting over a 6 month period.
Many Thanks In Advance
Tom