I am facing one unbelievable issue, we are updating the project plan using
QueueAddtoProject PSI. In this we are adding tasks under one summary task
(parent task) . Now as we are adding all new tasks under one parent task so
it should be visible in Project Professional. When we are looking into
project professional … few tasks can be seen under the other task but rest
all tasks are coming properly. (we have also checked programmatically the
parent id of all newly added tasks is same).
But this issue is not seen via Project center. All the new tasks can be seen
under proper parent task. It shows the correct view.
Regards,
virsharma
I am facing one unbelievable issue, we are updating the project plan using
QueueAddtoProject PSI. In this we are adding tasks under one summary task
(parent task) . Now as we are adding all new tasks under one parent task so
it should be visible in Project Professional. When we are looking into
project professional … few tasks can be seen under the other task but rest
all tasks are coming properly. (we have also checked programmatically the
parent id of all newly added tasks is same).
But this issue is not seen via Project center. All the new tasks can be seen
under proper parent task. It shows the correct view.