Hi,
We use Project Server 2007 (with SP1 and Infrastructure Update). Recently 2
PMs have complained that their Task Hierarchy was messed up after making
relatively minor modifications to their projects like adding a task, saving
and reopening.
The symptom is that leaf tasks have been re-parented to other parent tasks +
empty rows showed up.
Has anyone seen this problem? Is there a way to solve this?
ashwin
We use Project Server 2007 (with SP1 and Infrastructure Update). Recently 2
PMs have complained that their Task Hierarchy was messed up after making
relatively minor modifications to their projects like adding a task, saving
and reopening.
The symptom is that leaf tasks have been re-parented to other parent tasks +
empty rows showed up.
Has anyone seen this problem? Is there a way to solve this?