Task in Resource Timesheet is not visible

  • Thread starter Shiva Chaitanya
  • Start date
S

Shiva Chaitanya

Hi

We are using Project Server 2003.

Resource was unable to see the task in his timesheet.

With administrator login (Resources -> Adjust actuals), I am able to see the
task in his timesheet.

Can anybody please let me know why this resource is unable to see the task
in his timesheet and the same task is viewable to other resources assigned
against that task.

Any ideas on this would be appreciated.

Thank you
Shiva Chaitanya.
 
D

Dale Howard [MVP]

Shiva --

Does the user have the Current Tasks option selected on his View My Tasks
page, by chance? Let us know.
 
S

Shiva Chaitanya

Hi Dale

In my tasks page, the user has "all tasks" option selected. It is not
visible still. Any ideas on this?

Thank you
Shiva Chaitanya.
 
D

Dale Howard [MVP]

Shiva --

Is the resource in question a Proposed resource in the project? Let us
know.
 
S

Shiva Chaitanya

Hi Dale

As always, you are the best man. Just clicked "Ctrl+t". It clearly showed
that resource was proposed.

No idea how he got proposed in the project schedule. I changed the booking
type to committed.

Thank you very much.

Shiva Chaitanya.
 
D

Dale Howard [MVP]

Shiva --

Thanks for your kind compliment, my friend! :) And you are more than
welcome for the help.
 