D
Dave
I've created a "project" on the MSP 2003 server which basically
consists of links to important milestones from other projects. The
only info that seems to come with the linked tasks is the "Project"
field info (i.e. the project_name.published). I'd like to see other
info related to the projects of the linked tasks (e.g. the "project
state" - which is an enterprise custom outline code with choices such
as proposed, active, etc.).
Is the "project" field the only field that "comes with" externally
linked tasks? Is there any way get info from other fields to come with
them?
Thanks.
Dave
consists of links to important milestones from other projects. The
only info that seems to come with the linked tasks is the "Project"
field info (i.e. the project_name.published). I'd like to see other
info related to the projects of the linked tasks (e.g. the "project
state" - which is an enterprise custom outline code with choices such
as proposed, active, etc.).
Is the "project" field the only field that "comes with" externally
linked tasks? Is there any way get info from other fields to come with
them?
Thanks.
Dave