E
emq_33
Greetings All!
I am using Project 2007 and have a question regarding the data
displayed in the ballon when one puts the cursor over a task in Gantt
Chart View. Most of the data is self explanatory - task name, start,
duration, finish, etc. However, in the schedule I am working, the top
row of information in some balloons is gibberish (ie accented
characters, squares, etc) as if the data in the field is corrupt. In
other balloons, it is effectively a 'blank' line which I am guessing
means the field is blank. But I have no idea what the identity of the
field is causing this issue. Any thoughts?
For what it is worth, the Project file started as a v2000 file and was
upconverted when I started using Project 2007.
Thanks!
Don
I am using Project 2007 and have a question regarding the data
displayed in the ballon when one puts the cursor over a task in Gantt
Chart View. Most of the data is self explanatory - task name, start,
duration, finish, etc. However, in the schedule I am working, the top
row of information in some balloons is gibberish (ie accented
characters, squares, etc) as if the data in the field is corrupt. In
other balloons, it is effectively a 'blank' line which I am guessing
means the field is blank. But I have no idea what the identity of the
field is causing this issue. Any thoughts?
For what it is worth, the Project file started as a v2000 file and was
upconverted when I started using Project 2007.
Thanks!
Don