task lenght doubles when second resource is allocated

B

Bmack

Change the percentage of time the resource will spend on
the task to 5%.

-----Original Message-----
Hi folks. I have an issue with task lenghts and resource
allocation. I have a task that I've estimated taking 10
hours. I'd like to allocate two resources to it, with the
task length split between the 2 resources. When I
allocate the resources, however, the length of the task
double to 20 hours, with each resource allocated for 10
hours ear. If I add 4 resources, instead of allocating
2.5 hours each, the task time increases to 40 hours.
 