Need help linking two tasks. Task A (inspection services) should start 30
days prior to task B and finish 30 days after. Task B (construction) is
currently set for 24 months but probably will increase. Want to make sure
the duration of the services under Task A accurately increases in
coordination with the increase of construction duration. Tried linking A to
B with SS -30 days AND linking A to B with FF +30 days. Would not accept.
Suggestions? Thanks in advance.