task max resource work hours

R

ronjon

i have a resource who is available from 8 - 12am and 1 - 5pm, a total of
8 hours per day.
when i assign a task to this resource of 8h work the start and finish
dates differ 1 day (start on wednesday, finish on thursday). Why does
the task not start and finish on wednesday?

i have tried several work hours, but only at 7.5h and lower the task
starts and finishes on the same day.

my resouce availabilty units is set to 100%
 
D

Dave

Have you looked in the Task Usage view? That will show you where the
work lies. Typically this problem is caused because the work isn't
scheduled to start at 08:00 so it necessarily spans two days.

You may also want to look at the options under Tools/Options/Calendar as
this sets the default start and end time.

How are you entering the amount of work? Do you enter 8 hours or 1 day?
The conversion factors under Tools/Options/Calendar which define the
number of hours per day, the number of days per month etc also need to
be consistent with your calendar.
 