ronjon
i have a resource who is available from 8 - 12am and 1 - 5pm, a total of
8 hours per day.
when i assign a task to this resource of 8h work the start and finish
dates differ 1 day (start on wednesday, finish on thursday). Why does
the task not start and finish on wednesday?
i have tried several work hours, but only at 7.5h and lower the task
starts and finishes on the same day.
my resouce availabilty units is set to 100%
8 hours per day.