R
rooster99
Simple scenario:-
I have one task which is a 7 day workshop. I have two resources.
Resource 1 (£50/day) will be involved for the first 5 days & the second
resource (£30/day) will be the last 2 days.
How can I enter this in days for each resource. I don't want to be
entering 5/7's for res 1 and 2/7's as a percentage as this isn'#t
accurate for costing calculations. Can this be done and if so what is
the task type?
Thanks for any help.
I have one task which is a 7 day workshop. I have two resources.
Resource 1 (£50/day) will be involved for the first 5 days & the second
resource (£30/day) will be the last 2 days.
How can I enter this in days for each resource. I don't want to be
entering 5/7's for res 1 and 2/7's as a percentage as this isn'#t
accurate for costing calculations. Can this be done and if so what is
the task type?
Thanks for any help.