J
JohnV
I am running MS Project 2003 Standard. I am new to MS Project and VBA in MS
Project, but I have extensive experience in Access and Excel. Can some one
point me in the best way to achieve the follow.
1. A task (such as training) must be completed on 1 day. So, if I assign 1
day to the duration, then the training should start on the next available 8
hour day. The task should not flow across days.
2. A task (such as 3 training days) must be completed within the same work
week. If the that takes 3 days and the predecessor completes on a Wednesday
or later, then I want the task to look for the following Monday / Tuesday.
The reason I need to do this is because some persons who are needed at a
certain stage of a project will be required to undergo training. That
training can only be completed after certain predecessor tasks have been
completed. I want this calculation to be triggered whenever I change start
dates or durations of certain tasks. This will make sure that I do not have
to manually adjust the start dates.
Project, but I have extensive experience in Access and Excel. Can some one
point me in the best way to achieve the follow.
1. A task (such as training) must be completed on 1 day. So, if I assign 1
day to the duration, then the training should start on the next available 8
hour day. The task should not flow across days.
2. A task (such as 3 training days) must be completed within the same work
week. If the that takes 3 days and the predecessor completes on a Wednesday
or later, then I want the task to look for the following Monday / Tuesday.
The reason I need to do this is because some persons who are needed at a
certain stage of a project will be required to undergo training. That
training can only be completed after certain predecessor tasks have been
completed. I want this calculation to be triggered whenever I change start
dates or durations of certain tasks. This will make sure that I do not have
to manually adjust the start dates.