task must start on specific day of week.

M

mttakimbo

Hello all,

Forgive me if this question has an obvious answer, but I have a task
that can only happen on a specific day of the week. Whats the best way
to set the task so that whenever the previous task finishes, Project
will automatically move this one to start on the next Wednesday?

Am I asking too much?

thanks,

Brian
 
R

Rod Gill

Hi,

You need to create a new Calendar that only has Wednesday as a working day.
(Tools, Change Working time)
In the Task's Information dialog (Press Shift+F2 to display) select the
Advanced tab then assign the new Wednesday calendar to the Task. Now the
only working time for the task is Wednesdays.

--

Rod Gill
Project MVP

Project VBA Book, for details visit:
http://www.projectvbabook.com

NEW!! Web based VBA training course delivered by me. For details visit:
http://projectservertraining.com/learning/index.aspx
 
M

mttakimbo

Hi,

You need to create a new Calendar that only has Wednesday as a working day.
(Tools, Change Working time)
In the Task's Information dialog (Press Shift+F2 to display) select the
Advanced tab then assign the new Wednesday calendar to the Task. Now the
only working time for the task is Wednesdays.

--

Rod Gill
Project MVP

Project VBA Book, for details visit:
http://www.projectvbabook.com

NEW!! Web based VBA training course delivered by me. For details visit:
http://projectservertraining.com/learning/index.aspx

---------------------------------------------------------------------------­-------------------------








- Show quoted text -

Rod, thanks for your quick response, thats a great idea.
 