Hi

We have several projects within a server. (Not linked)

On One Plan if you roll up a series of activities, when you expand the
roll up bar again all task down the project from that point on loose
the Task Name Description.

The small +/- is still there for all the rollup bars within the rest
of the plan along with dates and information in other collumns its
just the task Name that Vanishes.

You have to go back to a previous back up and re-install the plan to
get the data back

Thanks in Advance
 
E

EPMLearner

Hi Paul,

I know that someone must call to obtain the hotfix but is there a
description of everything that they fix prior to making that call?
 