Hi,

We are using MSP Pro 2003 with SP2 and tried SP3 to see if can address the
following problem with no luck so far. On several occaisions a couple of our
users have experienced the same problem--the Task Names have disappeared
while working on the file. Collapsing the project or summary rows does NOT
refresh and make the task names reappear.

Your support would be greatly appreciated.

/Spiro Theopoulos.
 
R

Rod Gill

Hi,

If you click on the Task Name cell, is the text still in the formula bar? If
yes, there may be a white text color on white background problem. Check Text
styles as well as the font.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
S

ST

No. The text is completely gone. I think Trevor has the answer. I
suspected it may be that the files were on LAN drive.
 
S

ST

Thanks very much Trevor! I think you are right.

Trevor Rabey said:
This happens because you are on a network and your project file is stored on
a HDD on the network rather than local HDD, and your pc loses network
connection, perhaps just momentarily, while you have the file open.
Best to copy the file to the local HDD, work on it and then put it back on
the network.
Also, save each day's version every day, both as a backup and so that you
save the history of the planning.

Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING
www.perfectproject.com.au
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top