J
John de Rooy
Hello all,
I have a problem with tasks where I want the task to be not interrupte
by 'non-working time'.
Let me try to explain. I have several tasks with a duration of 2 day
that all are linked to eachother (FS). These are chemical processe
that have to be monitored by a person. The resource (person) has
standard calendar, meaning that he/she does not work weekends. So, m
problem really is that if a task is planned to start on a friday i
should be postponed till monday so that the person can monitor it for
consecutive 'working days'.
I know i can manualy put a constraint on it but I want it automated.
It would be no problem if anyone points me in the direction o
VBA-code, but I was wondering if MS Project tasks have a setting tha
already takes care of that.
Any help will be appreciated.
My second question to you all is how I can easily unsplit all task
that have been manualy split (I find this less important, but woul
also appreciate any input).
Kind regards,
Joh
I have a problem with tasks where I want the task to be not interrupte
by 'non-working time'.
Let me try to explain. I have several tasks with a duration of 2 day
that all are linked to eachother (FS). These are chemical processe
that have to be monitored by a person. The resource (person) has
standard calendar, meaning that he/she does not work weekends. So, m
problem really is that if a task is planned to start on a friday i
should be postponed till monday so that the person can monitor it for
consecutive 'working days'.
I know i can manualy put a constraint on it but I want it automated.
It would be no problem if anyone points me in the direction o
VBA-code, but I was wondering if MS Project tasks have a setting tha
already takes care of that.
Any help will be appreciated.
My second question to you all is how I can easily unsplit all task
that have been manualy split (I find this less important, but woul
also appreciate any input).
Kind regards,
Joh