Task not required

B

Bordoy

In my schedule I have a few tasks that are not my responsibility. I do not
want to delete so I can track but do not want it to impede 100% completion.
Is it possible to still show the task?
 
J

Jan De Messemaeker

Hi,

Show where?
If yopu mean just in the task list, set duration to 0 then in Task
Information, advanced, cross out "Mark task as milestone"
But then it will not be visible in the Gantt Chart.
Otherwise, just show the expected duration and when they're done set to 100%
complete

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
J

Jim Aksel

This might be obvious - also make sure to remove all resources from the task
if you don't want these costs to roll-up.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 