Some tasks from the project plan do not appear for a resource when they are
trying to update % complete. They are in his timesheet and in the project,
he has assignments (5%) and remaining work. One task is in the past; another
is due this week. We are using Project 2007 and Server 2007.
 
D

Darrell

Stacy,

Another reason I have seen this happen is the schedule having two names for
the same resource and the tasks in question are assigned to the
non-enterprise name. Just a thought.

Darrell
 
D

Darrell

Stacy,

Just another suggestion to help trouble shoot, can you enter % complete into
the timesheet where the tasks do appear and then inport to my tasks?