Some tasks from the project plan do not appear for a resource when they are
trying to update % complete. They are in his timesheet and in the project,
he has assignments (5%) and remaining work. One task is in the past; another
is due this week. We are using Project 2007 and Server 2007.
trying to update % complete. They are in his timesheet and in the project,
he has assignments (5%) and remaining work. One task is in the past; another
is due this week. We are using Project 2007 and Server 2007.