Hi there,

Does anyone know where the task notes of the Project
Server, are allocated in the SQL Server Database? I would
like to query and export all the task notes in a file. Or
is there a way to export all the notes in Project
Professional?

Thanks in advance
 
D

Dale Howard

Charles --

The information you seek can be found in the MSP_Text_Fields table. You
could export the notes by writing a macro in VBA, or using an off-the-shelf
product such as Crystal Reports. Hope this helps.
 