Task Number Field Values Disappear on Publishing?

L

ldb

I would like to make use of several task fields (Text, Flag, Number), but on
publishing (MS Project Server 2007) the Number values are reset to zeros;
values in Text and Flag fields are preserved.

I would appreciate any solution or insights with this issue.

ldb
 
L

ldb

Text, Flags, and Number fields are set in a MS Project;

All but the Number fields have the same values after publishing to 2007
Project Server - via Project Server view; all Number fields are reset to 0.
 
L

ldb

No macros are running. F9 does not reset the numbers.

numbers are set manually to identify task sub collections.

ldb
 
A

Andrew Lavinsky

And no line of business integration or links to external files (Edit > Links)...?

No saving from 2003 to 2007 formats or back and forth?

Then I would have to say that I am stumped. Can't think of anything else
to try. You might want to repost this and see if you have any more suggestions.

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 
L

ldb

There are no links, no integrations; no saving between 2003 and 2007 formats

Andrew - thanks for taking your time in considering this issue.

ldb
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top