A
am_yousef
I have a web application developed by "Visual Studio.NET 2003".
I am using "Microsoft Project Server 2003", and "Microsoft Office Project
2003"
Using my web application i will change the Task Percentage Complete in a
certain task in a project.
This could be done by changing the ("TaskPercentComplete" field in the table
called "MSP_VIEW_PROJ_TASKS_STD") in the Project Server DB.
After changing the (task percent complete) in the "Project Server DB"
through my application,
I open the Project Web Access (PWA),
click on the "Projects" link,
choose a certain project,
choose the "Tasks Summary" view,
Then i can see this change in the column called ("% Complete") for this
project.
But i can not see this change when i open this Project Plan through the
"Microsoft Office Project 2003".
So what i need,
Is that when i change the (Task Percent Complete) for a certain Project in
"the Project Server DB" through my .NET Application,
This change affects the "Task Percent Complete" (% complete) when i open
this Project Plan through the "Microsoft Office Project 2003".
Any help would be appreciated.
I am using "Microsoft Project Server 2003", and "Microsoft Office Project
2003"
Using my web application i will change the Task Percentage Complete in a
certain task in a project.
This could be done by changing the ("TaskPercentComplete" field in the table
called "MSP_VIEW_PROJ_TASKS_STD") in the Project Server DB.
After changing the (task percent complete) in the "Project Server DB"
through my application,
I open the Project Web Access (PWA),
click on the "Projects" link,
choose a certain project,
choose the "Tasks Summary" view,
Then i can see this change in the column called ("% Complete") for this
project.
But i can not see this change when i open this Project Plan through the
"Microsoft Office Project 2003".
So what i need,
Is that when i change the (Task Percent Complete) for a certain Project in
"the Project Server DB" through my .NET Application,
This change affects the "Task Percent Complete" (% complete) when i open
this Project Plan through the "Microsoft Office Project 2003".
Any help would be appreciated.