Task Predecessors disappear on import of Resource Table

C

cgoetz

rohave a project in which we want to be able to do an excel export of the
resource table and then be able to import the table back in to "restore" the
original resource table. My porblem is that when I import the original
exported resource table all of my task predecessors disappear! Everything
else seems to be correct. The resource table information is imported
correctly.
I am using MSP 2007 Pro and the schedule is not an Enterprise schedule.
Any help would be appreciated.

Regards,
Charles Goetz
 
S

Stephen Sanderlin

This is a known issue in WinProj07... It should have been fixed in the
IU (http://support.microsoft.com/kb/953751). If your PS deployment is
not currently using this level (client and server) your administrators
should consider upgrading.

--
Stephen Sanderlin
VP of Technology
MSProjectExperts

For Project Server Consulting: http://www.msprojectexperts.com
For Project Server Training: http://www.projectservertraining.com

Read my blog at: http://www.projectserverhelp.com
Join the community at: http://forums.epmfaq.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top