I'm more used to using Primavera, but I've been scheduling projects for some
time now. One issue I have is task progress. In P3, when a task is started
and not progressed, as the data date moves, the task end date moves, assuming
the remaining duration (either calculated or posted) is accurate.
In MSP, the start and end dates seem to just sit there, and remaining
duration is not an available field to post. I can post 99% complete on the
first day of a 60-day task, and the end date sits there. Any advice? Am I
looking in the wrong place?