Hey,

I imported my timesheets at the 'My Tasks' page, saved and submitted it.

The task progress has changed on 'My Task' page, but how can you see this
changes in the Project Center? Must the project manager approve anything ?

Thanks,
Koen
 
B

Ben Howard

Hi Koen,
In the my tasks, you must select and submit the tasks, the PM must approve
the updates and then publish the plan, and then the changes will show in PWA.
 