i am admin of MSPS 2007.i have 2 question.
1)my users create their timesheet and import it in MY TASK page and submit
it.when they want to create new timesheet the last task that they import it
for progress,appears with planned duration.i dont want it appears.
why this happen and how can i modify it?
2)when i import a timesheet for progress and after that i delete it ,i
expect i cant see its progress in my tasks page but it doesnt chage.how can i
refresh the import task for progressing and change it?
3)plz tel me steps of import a task for progress(not a timesheet)?
4)sometimes when i want to create my timesheet with my planned tasks i cant
enter actual work of my task.why?how can i modify it?
thanks alot my friend :)
 