Task Progress

M

Mousa

Hi,

am using project server in our organization and i have problem if anyone can
help me to fix it,

for example
let we say that there is a task started in 1/13/2008 and finished in
1/14/2008 - 2d, 8h/d
if i go to Assignment Details and see the total work it will be 2 and 100%
complete, but in the calender view below where the resource put his actual
work if i trace the actual work i calculate only 8h in 1/13/2008 and there is
0 actual work in 1/14/2008, check the (Transaction Comments and Task
History) see that the resource update 8h in 1/3/2008 and 8h in 1/14/2008 and
the PM approve it, then i checked the project plan if it publish i see that
it's publish to.
but this data not appear in both Assignment Details page and olap report.

any idea about what may be happend????
 