Mousa
Hi,
am using project server in our organization and i have problem if anyone can
help me to fix it,
for example
let we say that there is a task started in 1/13/2008 and finished in
1/14/2008 - 2d, 8h/d
if i go to Assignment Details and see the total work it will be 2 and 100%
complete, but in the calender view below where the resource put his actual
work if i trace the actual work i calculate only 8h in 1/13/2008 and there is
0 actual work in 1/14/2008, check the (Transaction Comments and Task
History) see that the resource update 8h in 1/3/2008 and 8h in 1/14/2008 and
the PM approve it, then i checked the project plan if it publish i see that
it's publish to.
but this data not appear in both Assignment Details page and olap report.
any idea about what may be happend????
am using project server in our organization and i have problem if anyone can
help me to fix it,
for example
let we say that there is a task started in 1/13/2008 and finished in
1/14/2008 - 2d, 8h/d
if i go to Assignment Details and see the total work it will be 2 and 100%
complete, but in the calender view below where the resource put his actual
work if i trace the actual work i calculate only 8h in 1/13/2008 and there is
0 actual work in 1/14/2008, check the (Transaction Comments and Task
History) see that the resource update 8h in 1/3/2008 and 8h in 1/14/2008 and
the PM approve it, then i checked the project plan if it publish i see that
it's publish to.
but this data not appear in both Assignment Details page and olap report.
any idea about what may be happend????